It’s time to choose visionary new faces in this election

As the country prepares for the upcoming general election, political parties have once again started their campaigns. Leaders are busy

The philosopher mentor

For a boy born in a quiet laid-back village of eastern Nepal, where you could lay down on a boulder

Why the 2006 Comprehensive Peace Agreement was deeply flawed

Usually, a peace agreement is reached between two or more countries at war. A common practice is to bring the

A conversation on ethical AI and future of learning with Deep Bikram Thapa Chhetri

Will humanity be better off thanks to artificial intelligence? This is one of the most defining issues of our times

Root of corruption: Ministerial positions and expensive election expenditures

Nepal has come to a point where it is necessary to seriously reconsider the long-standing practice of appointing ministers from

Tanahun hydropower project sees above 50 per cent progress

Damauli: The Tanahun hydropower project with a capacity of 140 MW has achieved a progress of 58.1 percent.

The work on the hydropower project is being carried out in three packages, and 52.07 percent financial progress has been achieved, said project chief Shyamji Bhandari.

Likewise, 35 percent progress has been made in the construction of structures including dams under package-1. 59 percent progress in the construction of power plants under package-2 and 73.5 percent of the construction of transmission line under package-3.

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan.