Comparing two coalition cultures: Case of Germany and Nepal

Germany’s coalition building functions very differently from the one in Nepal. After an election we have exploratory discussions, called Sondierungsgespräche

Climate change poses a threat to national security. What should Nepal do about it?

Most countries have finally realized the challenges posed by climate change to national, regional and global security. The justification for

A modest proposal for reviving Nepal’s economy

Mia, an abstract expressionist artist, walked through the vibrant streets of Mokum, to get inspired to create a new painting

COP29 |Climate activist Shreya KC explains what’s going wrong with the world and Nepal and what should be done

Over the last few months, I had a series of conversations with Shreya KC, one of the most prominent climate

Readiness, resilience, risk and response

The relationship between humanity and nature has always been delicate. Nature serves as both a provider and an adversary. Despite

Progress report on MCC projects: Second 400kV substation construction contract signed

Once completed, Ratmate Substation will have a capacity of 1000 Mega Volt Ampere making it one of the largest substations in the country.

From left to right: Diane L Francisco, RCD, MCC, Khadga B Bisht, ED, MCA-Nepal, Rajiv Agarwal, Director Commercial, TEECL and Shalini Tripathi, DED, MCA-Nepal

Kathmandu: MCA-Nepal has awarded and signed a contract with Techno Electric and Engineering Company Ltd, India to construct a 400 kV Substation at Ratmate in Belkotgadhi Municipality -7 in Nuwakot district as part of implementing Millennium Challenge Corporation (MCC) Nepal Compact. The 400 kV Gas Insulated Switchgear (GIS) substation will be constructed within the contract duration of 39 months. Once completed, Ratmate Substation will have a capacity of 1000 Mega Volt Ampere making it one of the largest substations in the country. The new US$ 51.6 million Ratmate Substation will serve as a critical interconnection of power transmission between the Lapsiphedi and New Hetauda Substations.

Khadga Bahadur Bisht, Executive Director at MCA-Nepal, and Rajiv Agarwal, Director- Commercial at Techno Electric and Engineering Company Ltd, India signed and exchanged the contract in the presence of MCC and MCA-Nepal officials. With the execution of this contract, MCA-Nepal has signed two of the three substations construction contracts planned under the MCC Nepal Compact.

Kulman Ghising, Managing Director of Nepal Electricity Authority, congratulated the MCA-Nepal team and stated, “The 400 kV Ratmate Substation, as envisioned in the Transmission System Development Plan of Nepal (TSDPN) is a critical component of Nepal’s national power transmission system and yet another milestone in MCC Nepal Compact’s contribution to the energy sector in Nepal.”

Congratulating MCA-Nepal on the achievement, Diane L Francisco, Resident Country Director of Millennium Challenge Corporation (MCC) said that the signing of the Ratmate Substation, the second of the three substations, marks a significant stride forward as the MCC Nepal Compact builds momentum in its implementation. “Over the next few years, we are confident that the progress of the MCC Nepal Compact will provide critical contributions to Nepal’s growing energy sector, helping meet Nepal’s evolving needs, bolstering Nepal’s immense potential, and bringing prosperity to the Nepali people,” she said.

MCA-Nepal Executive Director Khadga Bahadur Bisht said that MCA-Nepal is expediting all works for the construction of the substations and transmission lines under the Electricity Transmission Project funded by the US government’s Millennium Challenge Corporation (MCC) and the government of Nepal. “The contract for the third substation in Damauli is in the pipeline and the bids for the 18 km cross-border line are under evaluation,” he said. “We are also at the final stages of the procurement process to invite bids for the construction of the remaining portion of the transmission line as well.”

The 400kV Ratmate Substation will also have evacuation capacity of around 3,200 MW of power from hydropower projects and substations. The reliable power at various voltage levels at the substation will be available for distribution in Nepal to enhance industrial and commercial activities.

Along with three substations, the MCC Nepal Compact will fund the construction of up to 315 km of transmission line from Lapsiphedi, Kathmandu to the Nepal-India border in Nawalparasi (Bardaghat Susta West) under the Electricity Transmission Project. The bids for the 18 km cross-border transmission line have been received for evaluation. MCA-Nepal aims to award the contract in August. Likewise, preparations are on track to ensure the bids for the remaining 297 km of transmission lines are relaunched at the earliest possible this year.