Panama hosted a crucial Climate Week. Can Kathmandu follow suit?

As I am writing this piece, if someone wants to follow the latest developments on climate negotiations governance, Nepal is

Disconnected: Youth, AI, and Nepal’s parliamentary void

The debates in Nepal’s parliament feel like they’re stuck in a time warp. The language, the concerns, the political theater

When the earth shook, the service remained steady: Leading through ruins

On April 25, 2015, Nepal was struck by a devastating 7.8-magnitude earthquake — the worst disaster to hit the country

The legend of Singha Sartha Aju

Singha Sartha Aju, also known as Simhasartha Bahu, is a revered figure in Nepali folklore, particularly among the Newar community

Everything you need to know about Nagaloka and serpent kings in prehistoric Kathmandu Valley

In Hindu and Buddhist mythology, the Kathmandu Valley was once home to a vast lake known as Nagadaha, the home

MCA-Nepal signs contract to construct 400 kV New Butwal Substation

The 400 kV Gas Insulated Switchgear (GIS) substation will be constructed within the contract duration of 39 months.

Nawalparasi: In a milestone achievement, MCA-Nepal has awarded and signed a contract with Linxon India Pvt Ltd for the construction of the 400 kV New Butwal Substation in Nawalparasi (Bardaghat Susta West) district in Lumbini Province. The 400 kV Gas Insulated Switchgear (GIS) substation will be constructed within the contract duration of 39 months.

Kul Man Ghising, the Managing Director for Nepal Electricity Authority (NEA) and US ambassador to Nepal Dean R Thompson, local authorities and elected representatives were present at the signing ceremony in Bhumahi, Nawalparasi (Bardaghat Susta West) Thursday.

Speaking at the event, Ambassador Thompson stated, “The U.S. Government is committed to working with the Government of Nepal to ensure that the compact delivers on Nepal’s energy needs.” “The 400 kV New Butwal Substation will improve Nepal’s transmission capacity contributing to reliable and affordable electricity for household consumption, expanded commercial and industrial enterprises and cross-border electricity trading.”

On the occasion, NEA Managing Director Ghising said, “The 400 kV substation has been a priority for NEA and will supplement the existing 220 kV substation to significantly increase cross-border energy trade in the region.”

During the event, MCA-Nepal Executive Director Khadga Bahadur Bisht highlighted the overall progress being made in the implementation of the MCC Nepal Compact, stating “MCA-Nepal is expediting all works for the construction of the transmission lines and substations under the Electricity Transmission Project. We are at the final stages of the procurement process to sign the contract for the construction of the remaining two substations as well.”

Along with this substation, MCA-Nepal is constructing two other substations in Ratmate, Nuwakot district and Damauli, Tanahun district under the Electricity Transmission Project funded by the US Government’s Millennium Challenge Corporation (MCC) and the Government of Nepal. The contractors for the remaining two substations are being selected.

The MCA-Nepal Board, chaired by the Secretary at the Ministry of Finance, decided in its March board meeting to advance the 18 km Nepal portion of the New Butwal-Gorakhpur power transmission line to facilitate timely initiation of cross-border power trade as outlined in the agreement with India.